NEW QUESTION # 130
A person who already knows and understands the basics of loss prevention and security is known as:
- A. Engaged liaison
- B. Supportive person
- C. Review personnel
- D. None of the above
Answer: A
NEW QUESTION # 131
Constructability is NOT intended to:
- A. correct deficiencies in the project design
- B. optimize engineering and procurement
- C. balance project and environment goals
- D. integrate construction knowledge into the design
Answer: A
NEW QUESTION # 132
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
- A. 362 days
- B. 255 days
- C. 407 days
- D. 267 days
Answer: A
Explanation:
Understand the Concept of a Hammock Activity:
* A hammock activity spans over multiple activities and reflects the cumulative duration from the earliest start to the latest finish of the grouped activities.
Activities in the Hammock (6001-6003):
* Activity 6001: Duration = 102 days, FS relationship with successor.
* Activity 6002: Duration = 140 days, FS with 6001.
* Activity 6003: Duration = 115 days, FS with 6002.
Calculate the Duration:
* Earliest Start of Activity 6001 # Latest Finish of Activity 6003.
* Total duration = 102 + 140 + 115 = 362 days.
Cross-Verification with Answer Options:
* Option A: Incorrect. Overestimates.
* Option C: Incorrect. Underestimates.
* Option D: Incorrect. Underestimates.
* Option B: Correct. Matches the calculated duration.
NEW QUESTION # 133
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:
- A. Production output.
- B. Acceleration.
- C. Productivity efficiency.
- D. Productivity loss.
Answer: D
NEW QUESTION # 134
____________ builds on confusion when two or more people take advantage of their positions and the confusion to steal.
- A. Proliferation
- B. Accountability
- C. Invoicing
- D. Conspiracy
Answer: D
NEW QUESTION # 135
In communism, class struggle results in overthrowing capitalism and in radical Islam, faith struggle results in overthrowing of Russian capitalist society.
- A. False
- B. True
Answer: B
NEW QUESTION # 136
Which of the following project planning situations is the most frequent contributor to cost overruns?
- A. lack of detailed planning for operational start-up
- B. Inadequate definition of scope at the estimate (budget) stage
- C. Inappropriate definition of work breakdown structure
- D. Insufficient planning for change management
Answer: B
Explanation:
Impact of Scope Definition on Cost Overruns:
* Poor scope definition leads to unrealistic budgets and unforeseen changes, which significantly contribute to cost overruns.
* Other factors like change management and WBS definitions are secondary contributors compared to scope inadequacy.
PSP Study Guide References:
* The guide emphasizes scope definition as a critical factor for accurate budgeting and planning.
Conclusion: The correct answer is D, as scope definition at the estimate stage has the most frequent and significant impact on cost overruns.
NEW QUESTION # 137
Some people are willing to copy software and resell it or give it away; this authorized copying of copyrighted computer programs is called:
- A. Software privacy
- B. War driving
- C. Unauthorized access to software
- D. Identify theft
Answer: A
NEW QUESTION # 138
Making the most efficient before-the-loss arrangement for an after-the-loss continuation of business is called Risk Management.
- A. False
- B. True
Answer: B
NEW QUESTION # 139
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.
PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
"normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.
Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?
- A. $420,000.
- B. $552,000.
- C. $307,000.
- D. $524,000.
Answer: B
NEW QUESTION # 140
The sites that are partially configured but are missing the central computer are called:
- A. Frequent sites
- B. Warm sites
- C. Hot sites
- D. Cold sites
Answer: B
NEW QUESTION # 141
Which of the following is NOT a tool or technique used to perform scope planning?
- A. Schedule performance indexing.
- B. Alternatives identification.
- C. Benefit cost analysis.
- D. Expert Judgment.
Answer: A
Explanation:
Scope Planning Tools and Techniques:
* Tools for scope planning include methods to define and refine the project scope. These involve cost- benefit analysis, expert judgment, and alternatives identification.
* Schedule performance indexing is a performance tracking tool used during execution and is unrelated to scope planning.
PSP Study Guide References:
* Scope planning methods are detailed in the PSP guide, emphasizing tools like expert judgment, alternatives analysis, and structured decision-making techniques.
Analysis for Selection:
* Option A: A common method to analyze the costs and benefits of scope components.
* Option B: Incorrect. This is a tracking tool, not a scope planning method.
* Option C: Expert judgment is a key technique in defining project scope.
* Option D: Alternatives identification supports exploring various approaches to project goals.
Conclusion: The correct answer is B, as schedule performance indexing is not a scope planning tool.
NEW QUESTION # 142
______________ has been defined as the impact of a loss as measured in dollars.
- A. Corruptness
- B. Immorality
- C. Criticality
- D. Loss reserves
Answer: C
NEW QUESTION # 143
The project team must communicate the project plan, goals and objectives to all stakeholders to ensure the stakeholders understand the plan, goals and objectives and then continue this communication throughout the project life Which statement below would stakeholders NOT be expected to contribute?
- A. Stakeholders review the basis the schedule after the schedule is developed
- B. The key to successful acceptance by all stakeholders is a set of well-defined goals and objectives which should be Identified early in the planning process
- C. Stakeholder communication should be the single most Important objective of a program of key cost and schedule performance indicators (KPls)
- D. Early in the planning process, a set of well-defined goals and objectives is reviewed by the stakeholders
Answer: A
NEW QUESTION # 144
In which approach of comparative negligence, the plaintiff may collect something for injuries even if he or she was primarily responsible for the injuries?
- A. Pure approach
- B. 51 percent rule
- C. 50/50 rule
- D. None of the above
Answer: A
NEW QUESTION # 145
......