NEW QUESTION # 64
Which of the following best describes a traffic light auction format?
- A. Supplier submit decreasing bids within serial lots with durations displayed via color coded icons
- B. Supplier submit decreasing bids within staggered lots that do not include overtime
- C. Supplier submit decreasing bids and receive feedback on whether their bid will be considered via color coded icons.
- D. Supplier must pass an access gate with prerequisites before participating in the full auction
Answer: D
NEW QUESTION # 65
Which of the following content items can be created as a prerequisite to view event content?
- A. Attachment
- B. Lot/Lineltems
- C. Question
- D. Requirment
Answer: C
NEW QUESTION # 66
How can a customer run reports that identify the business units assigned to each sourcing project? There are 2 correct answers to this question.
- A. Use one of the existing header fields, such as Departments.
- B. Add a new question to the full sourcing project template.
- C. Use the Ship To data for the creator of the sourcing project.
- D. Create a custom header field and make this field reportable.
Answer: A,D
NEW QUESTION # 67
Which of the following templates are available with SAP Ariba Supplier Information and Performance Management (SIPM) new architecture enabled? Note: there are 2 correct answers to this question.
- A. Preferred supplier template
- B. Supplier qualification template
- C. Supplier request template
- D. Supplier registration template
Answer: C,D
NEW QUESTION # 68
What are the available event types when creating a quick project? Note: there are 3 correct answers to this question.
- A. Auction
- B. RFQ
- C. RFP
- D. RFx
- E. RFI
Answer: A,C,E
NEW QUESTION # 69
You are creating a new sourcing event.
When would you create and import event content via Microsoft Excel? Note: there are 2 correct answers to this question.
- A. When an individual needs to contribute to content creation but does NOT have an SAP Ariba account
- B. When loading translations to event content
- C. When creating a large number of lots
- D. When a supplier reports a technical issue and CANNOT submit their reponse
Answer: A,C
NEW QUESTION # 70
What solutions are included in the SAP Ariba Strategic Sourcing Suite? Note: There are 2 correct answers to this question.
- A. SAP Ariba Contracts
- B. SAP Ariba Buying and Invoicing
- C. SAP Ariba Spend Analysis
- D. SAP Ariba Supplier Lifecycle and Performance
Answer: A,D
NEW QUESTION # 71
A folder in the Sourcing Library contains highly confidential information. How do you ensure that this confidential information is only visible to authorized users?
- A. Set an access control on the folder
- B. Add the users to Team tab in the Sourcing Library
- C. Set a password on the folder
- D. Hide the folder in a subfolder
Answer: A,B
NEW QUESTION # 72
What difference can you view with the BOM comparison feature? Note: there are 2 correct answers to this question.
- A. BO Ms imported from the ERP and those created via CSV import
- B. Designed BOM and finished BOM
- C. Two distinct BOMs
- D. Different version of the same BOM
Answer: B,D
NEW QUESTION # 73
What are the different methods the team graders can use to grade responses? Note: There are 3 correct answers to this question.
- A. Grade by content
- B. Grade for consensus
- C. Grade offline using Excel
- D. Grade by team membership
- E. Grade by participant
Answer: A,C,E
NEW QUESTION # 74
What prepackaged report shows the total awarded spend for a specific organization across all event types?
- A. Supplier Participation Report
- B. Event Spend Summary
- C. Event Participation Summary
- D. RFI Report
Answer: B
NEW QUESTION # 75
You are configuring an approval task in a template. There is only one approver for the task. What are the advantages of creating the approver as a group instead of a user? There are 2 correct answers to this question.
- A. Ease of administration: It is easier to add/remove users to or from groups than it is to change the task.
- B. Notifications: You can only configure the notifications for groups, not for users.
- C. Delegation: Users cannot delegate approval tasks to others unless they are in the same group.
- D. Future-proofing: You may want to have multiple approvers in the future.
Answer: A,D
NEW QUESTION # 76
Which auction setting prevents a tied or near-tied lead bid?
- A. Improve bid by nominal amount
- B. Bid decrement
- C. Front buffer and back buffer
- D. Market feedback rules
Answer: C
NEW QUESTION # 77
In the enablement workbook, what does U* stand for?
- A. User iD for each licensed solution
- B. User licence applicable only to SAP Ariba Supplier information and Perfomance Management
- C. User licence for each licensed solution
- D. User licence applicable only to SAP Ariba Sourcing
Answer: C
NEW QUESTION # 78
What data is shared between all SAP Ariba modules?
- A. Units of measure
- B. Documents
- C. Comoddity codes
- D. Teams
- E. Groups
Answer: A,C,E
NEW QUESTION # 79
What does Shared Services build in a standard deployment?
- A. Up to 50 tasks/phases in the process
- B. Up to 5 custom header fields
- C. 1 analytical report
- D. 3 custom dashboard templates
- E. 1 sourcing request template
Answer: A,B,C
NEW QUESTION # 80
Why would you use the Integration Tool Kit?
- A. To eliminate the need to manually update data in Ariba to match ERP
- B. To transfer updates from an ERP system to SAP Ariba in real time
- C. To transfer updates from an ERP system to SAP Ariba on scheduled basis
- D. To ensure data is synchronized across all SAP Ariba applications
Answer: A,C
NEW QUESTION # 81
What is the maximum character length of the Department ID field?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION # 82
What format does SAP Ariba recommend for supplier user IDs?
- A. email address
- B. First initial; Last name
- C. Company name -Unique number
- D. First name; Last name
Answer: A
NEW QUESTION # 83
Which of the following factors would influences the success of an auction?
- A. Participants are bidding in multiple currencies
- B. Raw material prices for the suppliers are rising
- C. The supply base is competitive
- D. There are wide variations in product standards
Answer: C
NEW QUESTION # 84
......
SAP C-ARSOR-2308 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
Dumps Real SAP C-ARSOR-2308 Exam Questions [Updated 2024]: https://www.testpassking.com/C-ARSOR-2308-exam-testking-pass.html
Free C-ARSOR-2308 Exam Dumps to Pass Exam Easily: https://drive.google.com/open?id=16fA_x8TDmuOyAkcs-sZi9LLX5qHL4lxK